Quote a distribution board replacement for an owners corporation
You are an Estimator and Project Electrician in Electrical Contracting.
What has happened
The thermal imaging survey at Harbourview Apartments, job J-26-1152, found two hot joints on the neutral bar of the level 8 distribution board. The owners corporation has asked for a quotation to repair the joints immediately and to replace the level 8 board with a new board that provides residual current protection on every final sub-circuit. The board supplies twelve apartments' common area circuits, the level 8 corridor lighting, fire door holders and a lift lobby air conditioner. Any outage must be arranged with the building manager and residents notified forty-eight hours ahead. The riser is tight and access is through a locked cupboard. The Electrical Contracting Manager will review the draft before it is sent.
Deliverables
- Completed quotation on the template with scope, price, exclusions and program
- Materials list and labour estimate
- Outage and access plan
- New job board record and cover note to the customer
Documents to use
Systems to use
Job and Work Order Board
The record of every quoted, scheduled, in-progress and completed job across all departments, with the site, allocated tradespeople, supervising electrician and status.
Test and Compliance Register
Records the mandatory test results, certificates of electrical safety, solar compliance documents and observations for every job before it is handed over.
Units of competency
Current on training.gov.au for the Electrotechnology Training Package as at 10 September 2026.
UEECO0015Provide quotations for installation or service jobsUEECO0017Source and purchase material/parts for installation or service jobsUEEEL0057Plan electrical installations with a low voltage demand up to 400 A per phaseUEECD0029Plan electrotechnology projectsUEEEL0003Arrange circuits, control and protection for electrical installationsQualifications
UEE42120Certificate IV in Electrotechnology - Electrical ContractingUEE50420Diploma of Electrical EngineeringWhat to look for
Evidence guide
Look for a scope that a customer could understand and a tradesperson could build from, a realistic outage plan that protects the fire door holders and residents, a priced materials list tied to the circuit schedule, and exclusions that limit the business's exposure without hiding anything. The testing and certification description must match the policy.